May 7, 2015 - Franchise Articles by |

KFC Corp. v. Kazi, Slip Copy, 2013 WL 2257606 (W.D.Ky. 2013)

A federal court in the Western District of Kentucky on May 22, 2013, decided in essence to wipe out the protections that had been given to a KFC franchisee in a formal written settlement agreement that had resolved a previous remodeling dispute between the franchisor and franchisees in the Kentucky Fried Chicken System. On May 2, 2011, the franchisee Defendants’ franchise agreements for its California stores were terminated when Defendants failed to comply with the agreements' express conditions and several remodel agreements. As part of the Settlement Agreement, KFCC reinstated Defendants' franchise agreements for three California stores, conditioned on Defendants remodeling the stores by certain deadlines. In this case, KFCC moved to enforce the parties' Settlement Agreement, asking the Court to order the franchisee to close the stores because the franchisee did not meet its remodeling obligations that had been reestablished in the settlement agreement.

The Settlement Agreement provided the consequences for Defendants' failure to remodel in a timely manner. In Paragraph 4(c), the Settlement Agreement stated: “If the upgrade actions set forth in paragraph (a) above are not completed within the Time Frame for any California Stores, the Respective Franchisees must close and complete for each non-upgraded California Store the De–Image Obligations as described in paragraph 12 below no later than thirty (30) calendar days after the respective Time Frame.” The franchisees did not meet this deadline, although they had what they viewed to be a valid legal excuse – that the government permitting authorities were themselves unable to produce the permits to the franchisees.

In this case, the franchisees did not argue that the language of the agreement did not require remodeling by a date certain; nor did the franchisees argue that this date had passed without the remodeling having been completed. Instead, the franchisees argued that Paragraph 4(b) of the Settlement Agreement “provides for extensions of the six month time frame where there has been a permitting delay. Specifically, the franchisees argued that “staffing shortages and significant delays within the permitting entities have caused their failure to remodel the stores in the pertinent time frame.” The franchisees, based on the above, argued that the permitting authorities would need a couple of more months to provide the necessary permits and that accordingly their deadline for completing remodeling should be extended.

Rather than accepting this reasonable explanation for the delay, and ruling to fairly allocate the effects of the permitting delay (which ironically the parties had anticipated) the Court dug down into the minutiae of the Settlement Agreement and “found” that there were certain very specific sub-deadlines about which the franchisee had to have made notification to be able to avail itself of the permitting-delay exception. Specifically, “Defendants needed to have provided documentation that they applied for permits within one week of KFCC's approval of the architect's specifications, and they also needed to have provided proof that Defendants satisfied all permit requirements within one week after a permitting entity's request. And, the required documentation must have been provided within one week from their notice of a permit delay.”

At the end of the day, the Court appeared not willing to help the franchisees obtain the benefits of their permitting delay clause in the Settlement Agreement solely because the franchisees had failed to carry out certain ministerial notice provisions of that protective clause. Ultimately the Court ruled that the permitting delay – the real villain in the loss of the franchises – would not be held legally accountable for the remodeling delay. “The Court finds that under the Settlement Agreement's clear terms, a delay by the permitting authorities does not automatically excuse Defendants' failure to meet the remodeling deadline.” Franchise remodeling terminations are relatively common in the fast-foot franchise world.

Case Excerpt

KFC Corp. v. Kazi, Slip Copy, 2013 WL 2257606 (W.D.Ky. 2013)

MEMORANDUM OPINION AND ORDER

JOSEPH H. McKINLEY, JR., District Judge.

This matter is before the Court on Plaintiff KFCC's Motion to Enforce Settlement Agreement to Close the California Stores [DN 48]. Fully briefed, this matter is ripe for decision. For the following reasons, Plaintiff's motion is GRANTED.

I.

BACKGROUND

Defendants are franchisees of KFC Corporation (“KFCC”). They operate numerous KFC stores across the United States, including three stores in California. On May 2, 2011, Defendants'

franchise agreements for the California stores were terminated when Defendants failed to comply with the agreements' express conditions and several remodel agreements. (See Compl. [DN 1] ¶¶ 52–70.) In August 2011, KFCC brought this lawsuit against Defendants, alleging that they violated their franchise agreements with respect to the California stores.  (See Id. ¶¶ 80–96.)Thereafter, the parties engaged in settlement discussions, ultimately executing a Settlement Agreement on May 8, 2012. The parties' Settlement Agreement was made part of an Agreed Judgment [DN 30] in this case, ensuring that the Court would retain jurisdiction to resolve disputes related to the settlement.

As part of the Settlement Agreement, KFCC reinstated Defendants' franchise agreements for the three California stores, conditioned on Defendants remodeling the stores by certain deadlines. (See Settlement Agreement [DN 34] ¶ 4.) With respect to the remodeling, the Settlement Agreement provided that Defendants could elect which two of the three stores to remodel within a six-month time frame. Remodeling of the remaining store had to be completed within a nine-month time frame. (Id.¶ 4(a).) Defendants elected to remodel the Arleta Restaurant, ID # H730008, and the Baldwin Park Restaurant, ID # H730109, within the six-month time frame, meaning that Defendants had to complete their remodeling by November 8, 2012. (See Aff. of Timothy M. Rook [DN 48–5] ¶¶ 3–4.) Before that deadline expired, Defendants requested a three-week extension. KFCC agreed to extend the deadline until November 29, 2012. (See Id. ¶ 4; Def.'s Resp. [DN 51] 4.) However, Defendants did not even begin to remodel the stores by that date. (See Aff. of Timothy M. Rook [DN 48–5] ¶ 5; Termination Letter [DN 48–4].)

*****************************

II.

DISCUSSION

In this case, KFCC has moved to enforce the parties' Settlement Agreement, asking the Court to order the closing of both the Arleta and the Baldwin Park Restaurants. In support, KFCC argues that Defendants have breached their obligations under Paragraph 4 of the Settlement Agreement by failing to timely remodel the stores. KFCC also argues that due to this failure, Defendants are operating both stores despite the expiration of their franchise agreements, infringing on KFCC's trademarks in violation of the Lanham Act.  (KFCC's Mem. in Supp. of its Mot. [DN 48–1] 7–8.) The parties do not dispute that the Settlement Agreement requires Defendants to close and de-image the stores when there has been a failure to timely complete remodeling. (Settlement Agreement [DN 34] ¶ 4(c).) They also do not dispute that several months have passed since Defendants were required to have completed the stores' remodeling.

In response to KFCC's motion, Defendants argue that Paragraph 4(b) of the Settlement Agreement “provides for extensions of the six month time frame where there has been a permitting delay.”(Defs.' Resp. [DN 51] 2.) According to Defendants, staffing shortages and significant delays within the permitting entities have caused their failure to remodel the stores in the pertinent time frame. (Decl. of Stephen E. Poludniak [DN 51–1] ¶¶ 5–6.) Defendants assert that the permitting entities have informed them that it may be several more months before permits are issued. Thus, Defendants contend that an extension of time for the permitting delay is appropriate. (Id.)

However, the Court finds that under the Settlement Agreement's clear terms, a delay by the permitting authorities does not automatically excuse Defendants' failure to meet the remodeling deadline.

**************************

(Settlement Agreement [DN 34] ¶ 4(b).) Under this language, Defendants must satisfy two conditions in order to claim an exception to the Time Frame based on a permit delay. First, Defendants must provide documentation that they applied for permits within one week of KFCC's approval of the architect's specifications. Second, documentation must be provided that Defendants satisfied all permit requirements within one week after a permitting entity's request. The documentation must be provided within one week from their notice of a permit delay. (Id.)

In its motion to enforce the Settlement Agreement, KFCC argues that Defendants have never provided documentation that there was a permit delay. Additionally, KFCC argues that Defendants have failed to provide documentation “that they timely applied for the building and other necessary permits … that they exercised best efforts in taking all other steps necessary to obtain the necessary permits … [or] that they satisfied all permit requirements within one week after a request by a permitting entity.”(Aff. of Timothy M. Rook [DN 48–5] ¶ 11.) Defendants have offered no evidence contesting these facts. FN1

FN1.In fact, Defendants do not argue that they have provided any documentation to KFCC relating to a permitting delay either prior to, or after, the November 29, 2012 deadline to complete remodeling.

According to Defendants, KFCC approved Defendants' remodeled drawings on September 17, 2012, which required them to apply for building permits within one week—by September 24, 2012. (Defs.' Resp. [DN 51] 3.) Thereafter, Defendants requested and were granted a three-week extension until October 15, 2012. Defendants admit that despite this extension, they failed to meet the intermediate deadline, as they did not submit the Arleta application until October 25, 2012 and did not submit the Baldwin Park application until October 29, 2012.(Id.) Thus, the first condition required in order to claim an exception to the Time Frame under Paragraph 4(b) was not satisfied. Under the parties agreement, the permit delay is deemed unreasonable.

Defendants suggest that this analysis is contrary to the parties' intent. Defendants highlight that the Settlement Agreement explicitly states that the franchise agreements shall be terminated for “any unreasonable permit delay or delay based on the Respective Franchisees' actions or inactions that results in a failure to remodel within the respective Time Frame.” (Settlement Agreement [DN 34] ¶ 4(b) (emphasis added).) According to Defendants, the delay is not based on their actions or inactions. Instead, staffing shortages and significant delays within the permitting entities have resulted in the failure to timely remodel the stores—not their “minimal delay in submission.”Defendants thus argue that terminating their franchise agreements is improper. Defendants cite  Keliher v. Cure,534 N.E.2d 1133 (Ind.Ct.App.1989), for the proposition that a preliminary, collateral deadline provision is not “of the essence,” even where a contract includes general language that time is of the essence. The Court finds, however, that this case is inapposite.

In Keliher v. Cure, an Indiana court held that a purchase agreement containing a “time is of the essence clause” was extended beyond the date set for the prospective purchaser's fulfillment of a financing condition. Id. at 1136.In so doing, however, the court relied heavily on the fact that “all parties to the transaction … considered the purchase agreement viable notwithstanding that the February 6 date had come and gone.”Id. at 1136.Here, Defendants have pointed to no evidence indicating that KFCC considered the franchise agreements to be valid even though they missed the intermediate deadline for submitting the permit applications. Defendants' reliance on this case is, therefore, without merit.

The Court reads Paragraph 4(b) to provide for the termination of the franchise agreements in two situations: (1) when there has been any unreasonable permit delay, as defined in Paragraph 4(b); and (2) when there has been any other kind of delay that is based on the franchisee's actions or inactions. In other words, any unreasonable permit delay that results in a failure to remodel within the time frame is grounds for termination of the franchise agreements. Any other kind of delay must be based on the franchisee's actions or inactions before it can give rise to termination. Here, there can be no question that the permit delay, which the parties agreed beforehand would be unreasonable, has resulted in a failure to remodel within the time frame. As such, it provides a basis for termination of the franchise agreements.

The Court notes that Defendants' argument pertaining to “formal notice” is without merit. In this regard, Defendants contend that they have not received “formal notice” of a delay by the permitting authorities. Defendants further contend that they are not required to—and simply cannot—request that KFCC extend the remodeling deadlines until “formal notice” is given. (Defs.' Resp.  [DN 51] 2.) In support, Defendants state that formal notice is required because they “do not yet know the potential duration of the permitting delay and because they cannot certify that no further actions by Defendants will be required in order for the permits to be issued….” (Defs.’ Resp. [DN 51] 2.) As KFCC correctly notes, however, Paragraph 4(b) of the Settlement Agreement neither mentions nor requires “formal notice.” Instead, it requires Defendants to satisfy Paragraph 4(b) within one week of receiving “notice” of a permit delay. (See Settlement Agreement [DN 34] ¶ 4(b).) Without a special contractual definition of the word “notice,” the Court finds that it takes on its ordinary meaning of “knowledge, acquired in whatever manner and for whatever purpose, of facts which would operate on the mind of any rational man of business, and make him act with reference to knowledge he has so acquired….” Sentry Safety Control Corp. v. Broadway & 4th Ave. Realty Co.,124 S.W.2d 1051, 1055 (Ky.1939)(citation omitted). Here, Defendants admit that they had actual knowledge that there would be delays throughout the permit review and approval processes. (See Declaration of Stephen E. Poludniak [DN 51–1] ¶¶ 5–6.) Despite this knowledge, Defendants nevertheless failed to provide any documentation to KFCC of the permitting delay.

Lawyer USA

Super Lawyers

Lawyer USA

Complex Commercial Litigation Law Firm of the Year – USA

Lawyer USA

Complex Commercial Distribution Litigation Representative

Lawyer USA

Antitrust & Franchise Law Firm of the Year – Washington DC

Lawyer USA

Best Franchise Lawyer of the Year – New York

Lawyer USA

Best for Franchise Disputes – USA

Lawyer USA

Complex Commercial Litigation Law (Franchisees and Dealers) 2021 – USA

Lawyer USA

Antitrust and Franchise Law Firm of the Year in DC

Lawyer USA

Leading Professionals in Law

Lawyer USA

Franchise Law
in the District of Columbia

Lawyer USA

Franchise Law Firm
of the Year – USA

Lawyer International

Lawyer International
Legal 100
2018

Lawyer International

Lawyer International
Legal 100
2019

ACQ5 LAW AWARDS 2019

US (New York)
Franchise Lawyer
of the Year
ACQ5 GLOBAL AWARDS 2019, JEFF GOLDSTEIN, GOLDSTEIN LAW FIRM, PLLC

ACQ5 LAW AWARDS 2019

US (New York)
Franchise Law Firm
of the Year
ACQ5 GLOBAL AWARDS 2019, GOLDSTEIN LAW FIRM, PLLC

Lawyers of Distinction logo

2020 Power Lawyers

Esteemed Lawyers of America Logo

Esteemed Law Firm Complex Litigation

Global Law Experts Logo

Recommended Firm in Franchise Litigation

Who's Who Attorney Logo

Top Attorney USA – Litigation

Avvo Franchise Lawyer Symbol

Superior Attorney in Franchising

Avvo Franchise Lawyer Symbol

Superior Attorney in Antitrust

Finance Monthly Global Award Winner Logo

Franchise Law Firm of the Year

Lead Counsel logo

Chosen Law Firm for Commercial Litigation

BBB of Washington DC

A+ Rated

Washington DC Chamber of Commerce

Verified Member

Lawyers of Distinction logo

Franchise Law Firm of the Year

ISSUU

Best Law Firm for Franchise Disputes in 2017

Law Awards Finanace Monthly

Franchise Law Firm of the Year - 2017

Top Franchise Litigator for Franchisees and Dealers

Top Franchise Litigator for Franchisees and Dealers

2017 Finance Monthly Award

2017 Finance Monthly Award

ACQ5 LAW AWARDS 2018

Franchise Law Firm
of the Year
ACQ5 LAW AWARDS 2018

ACQ5 LAW AWARDS 2019

Franchise Law Firm
of the Year
ACQ5 LAW AWARDS 2019

Franchise Law Firm of the Year

Franchise Law Firm of the Year

Franchise Law Firm of the Year

Franchise Law Firm of the Year
Global Awards 2017

Global Law Experts

Franchise Law Firm
of the Year
in New York – 2019

Finance Monthly Law Awards - 2018

Finance Monthly Law Awards - 2018

Franchise Law Firm of the Year

Franchise Law Firm
of the Year
Global Awards 2018

Contact Us

Goldstein Law Firm, PLLC

1629 K St. NW, Suite 300,
Washington, DC 20006

Phone: 202-293-3947
Fax: 202-315-2514

Free Consultation

Downtown Chicago Office

30 South Wacker Drive 22nd Floor #3341,
Chicago, IL 60606

Phone: 312-382-8327

Free Consultation

Free Consultation